On this page
Short answer
A UCC-3 termination is a public filing that terminates a UCC-1 financing statement and removes the lien from the public record. It is filed by the secured party after you pay or settle your secured debt. UCC section 9-513(c) provides that the secured party must terminate the financing statement by filing the UCC-3 or sending it to you within 20 days of your authenticated demand. If the UCC-3 is not filed, the lien remains visible in the public record.
Why it matters
An old lien can prevent you from getting a loan, selling your business, or even getting a bank account years after the debt has been paid. The UCC-3 is what your lender is looking for when they ask for proof.
Example
If a contractor in Dallas settles an MCA for $40,000, with its last payment paid on Mar 2, 2026, and the contractor sends a written demand for the UCC-3 on Mar 5, 2026, the funder will have 20 days, until Mar 25, 2026, to file the UCC-3 or send it to the contractor. If the funder does not do so, the contractor may file the UCC-3 and can seek to recover actual damages plus $500 statutory damages.
How it affects settlement
Whenever a business settles a debt with a secured creditor, the agreement should include a UCC-3 termination. The agreement should include the UCC-1 filing number(s) of all original UCC-1 filings and set a deadline following final payment. Instead of getting a promise, get the filed copy. Anytime a secured debt is assigned, it is also important that the current secured party of record file the UCC-3 termination.
Related terms
Questions about UCC-3 terminations
How long does a funder have to file a UCC-3 termination?
After the debt is satisfied, a funder has 20 days from the date of a debtor's authenticated demand to file or transmit a UCC-3 termination, as outlined in UCC §9-513(c). Authenticated demand refers to a signed or electronically verified written request. As a practical matter, the debtor should send the authenticated demand in a trackable manner and should retain proof of delivery.
What can I do if the funder will not file the UCC-3?
If a secured party does not act within 20 days of receiving an authenticated demand, the debtor can file the UCC-3 termination. The business must include a statement that the secured party failed to act within 20 days of receiving an authenticated demand (UCC §9-509(d)(2)). A business can also seek $500 in statutory damages for the failure to file the UCC-3 termination within 20 days of the authenticated demand.
Does a settlement automatically remove a UCC-1 lien?
No. Settling the debt does not, by itself, remove the UCC-1 lien. Instead, the lien remains a public record until a UCC-3 termination is filed. The settlement agreement should also require the funder to file a UCC-3 termination for each filing number within a certain number of days after the final payment.
Get a free review of your options
- Send us your agreements and your latest bank account statements.
- We'll review your funders, the terms and the legal exposure you face.
- You will receive a written summary of your options without obligation.
Related questions
Sources
- UCC §9-513, Termination statement — Legal Information Institute, Cornell Law School — www.law.cornell.edu/ucc/9/9-513 — Checked Nov 2026
- UCC §9-509, Persons entitled to file a record — Legal Information Institute, Cornell Law School — www.law.cornell.edu/ucc/9/9-509 — Checked Nov 2026
- UCC §9-625, Remedies for secured party's failure to comply with Article — Legal Information Institute, Cornell Law School — www.law.cornell.edu/ucc/9/9-625 — Checked Nov 2026